Architectural Services for new Saint John North-End K-5 School

Numéro de sollicitation 0675004-25

Date de publication

Date et heure de clôture 2023/06/01 12:30 HAE

Date de la dernière modification


    Description
    ****AMENDMENT # 4*****

    The following bid questions were received:

    Question #1:

    Will an extension to the closing date of the Request for Proposal be considered?

    Response #1:

    No

    Question #2:

    Category 2.1 requires Mechanical Engineer of Record to have undertaken a school project within the last 10 years having a construction value greater than $15M. Can this be reduced to $10M, similar to other educational RFP's within the last year.

    Response#2: Yes

    Question #3:

    Category 2.4 requires Structural Engineer of Record to have undertaken a school project within the last 10 years having a construction value greater than $15M. Can this be reduced to $10M, similar to other educational RFP's within the last year.

    Response#3: Yes

    All other information remains the same.

    ****AMENDMENT # 3*****

    The following bid question was received:

    Question #1:

    in Appendix I, RFP Technical Evaluation Criteria table, it seems to say that Category 1 responses should be limited to 3 pages. Category 1 includes 23 questions to be responded to and the questions alone take up 1.5 pages, is it reasonable to response to all these questions in 3 pages? That said, is it expected that the responses should be limited to 1 or 2 phrases

    Response #1

    Category 1 can have a page limit of up to 8 pages.

    All other information remains the same.

    *****AMENDMENT # 2*****

    The following bid questions were received:

    Question #1

    Reference to Amendment #1 Question #4 and Response #4:

    Question #1A)

    The response was "yes" to the need and an application of an evaluation score for the Elevator Consultant. What is their submittal requirement?

    Response #1A)

    Submit name, company and experience.

    Question #1B)

    How is this evaluated and what experience needs to be demonstrated?

    Response #1B)
    Required as part of RFP response.

    Question #1C)
    Similar to other sub-consultants?

    Response #1C)
    All sub-consultants are to be identified.

    Question #1D)

    What is the score (points awarded) for the Elevator Consultant?

    Response #1D)
    An elevator consultant is required as part of the proponent's design team.

    Question #1E)
    Does this required re-distribution of other scores/points?

    Response #1E)
    No

    Question #2)

    In 2020, there were 30 projects in the Maritimes registered under LEED v4 and none under LEED v4.1. Few consultants would be able to provide a completed LEED v4.1 reference school project. Please consider expanding your criteria to include: LEED v2009 schools and LEED v4 projects. It may be ideal to allow the inclusion of more than one reference project to show both

    Response #2)

    LEED v4 is acceptable

    All other information remains the same.

    *****AMENDMENT # 1*****

    The following questions have been received:

    Question #1
    The Appendix I Technical Submission is a PDF document. Are proponents to use this PDF as the submittal form or is there a modifiable Word Document that may be used, or can we reproduce the document ourselves?

    Response#1
    Proponents can use a PDF editor and use the PDF Form

    Question #2
    Is the Proposed Project Team Chart also to have information directly inserted or may this be replicated and then information entered for the submission (Word document or other file format)?

    Response#2
    It can be replicated.

    Question #3
    The Proposed Project Team Chart indicates 6 lines for 6 Team Members. Are these to represent only the 6 Team members (individuals who comprise Categories 1 through 3)) who are evaluated in Part E (RFP Score Evaluation)?

    Response#3
    Proponent can add lines if required.

    Question #4
    An Elevator Consultant is listed under 1.2.1 Intent. Is this a requirement in the design (ie expecting two floors). If so, are they to be listed in the Team Chart? Is there an evaluation score for the Elevator Consultant?

    Response #4
    Yes to all questions #4

    Question #5
    Related to the previous question, how are other team members and sub-consultants evaluated? Are they to be included in the Project Team Chart? Examples include: Cost Consultant, Acoustical Consultant, Commercial Kitchen Consultant, etc?

    Response #5
    Yes sub consultant should be included in Project Team Chart, Cost and kitchen consultant are part of basic service. Acoustic Consultant is an additional service.

    Question #6
    How are the team members within the Prime Consultant's firm considered/evaluated: Eg; Lead Technologist; Registered Interior Designer, Construction Administration Manager, etc? Are these Team members to be included in the Project Team Chart?

    Response#6
    The contract administrator shall be the AoR. Others are not evaluated. Yes team members should be included in the project team chart

    Question #7
    Is a Project Organization Chart permitted that provides all team members, Prime Consulting team and Subconsultants?

    Response#7
    Yes

    Question #8
    Are Project Team Members CVs to be included with the Submission (perhaps as appendices)? Would other team members such as those listed above also provide CVs?

    Response #8
    Yes CV's as appendices, Proponents decision to submit other team members.

    Question #9
    How are proponents to describe their proposed workplan? . Items such as consultations/meetings with DTI-BD and EECD, frequency, collaborations and presentation to the Planning Committee through design might be shared through a Proponent Schedule. Is this a requirement for Proposals?

    Response #9
    Yes, to all question #9


    Question #9
    It is understood that site meetings will be on-site. However, are design meetings all in-person?. Or is there a mix of in-person and online meetings that may be warranted given access to proven technology?

    Response #9
    All formal presentations and all meetings with authorities having jurisdiction must be in person.


    all other information remains the same.

    **********************



    This RFP is being conducted in accordance with the resulting Qualifying List from RFSO 0403004-23


    Architectural services for new SJ North-End
    K-5 School

    See attachments for complete
    details and instructions

    Durée du contrat

    Voir la description ci-dessus pour voir tous les détails.

    Accords commerciaux

    • Veuillez consulter la description ou les documents de l'appel d'offres

    Former un partenariat avec une autre entreprise

    La fonctionnalité permettant d'ajouter le nom de votre entreprise à la liste des entreprises intéressées est temporairement indisponible.

    Cette liste ne remplace pas et n'affecte pas les procédures de l'appel d'offres pour ce processus d'achat. Les entreprises doivent tout de même répondre aux demandes de soumissions et concurrencer en fonction des critères établis. Pour plus d'informations, veuillez lire les conditions d'utilisation.

    Coordonnées

    Organisation contractante

    Organisation
    Section des appels d'offres
    Adresse
    Centre regional de Fredericton
    Fredericton, Nouveau-Brunswick, E3A 2S4
    Canada
    Autorité contractante
    Robert Comeau
    Numéro de téléphone
    1 (506) 444-2542
    Adresse courriel
    bidquestionssoumissions@snb.ca
    Télécopieur
    1 (506) 444-4200
    Détails de l'offre

    Les détails complets de cette occasion de marché sont disponibles sur un site tiers

    Cliquez sur le bouton ci-dessous pour vous rendre vers ce site Web. Le site tiers pourrait exiger la création d’un compte personnel pour consulter l’occasion de marché ou pour soumissionner. Les informations reliées aux frais encourus pour accéder aux détails complets sont indiqués sous l’onglet Description.

    Admissibilité et conditions d’utilisation

    Les occasions de marché du gouvernement du Canada, ainsi que les avis d’attribution, les documents de sollicitations et autres documents sont disponibles sans frais sur AchatsCanada, sans devoir s’inscrire.

    Les informations peuvent être disponibles sur une autre source avant d'être disponibles sur AchatsCanada. Vous avez peut-être reçu ces informations via un distributeur tiers. Le gouvernement du Canada n'est pas responsable des avis d'appel d'offres ou des documents et pièces jointes qui ne sont pas accédés directement à partir d’AchatsCanada.canada.ca.

    Les appel d'offres ou avis d'attribution du gouvernement du Canada sont titulaire d’une licence du gouvernement ouvert - Canada qui régit son utilisation. Les documents de sollicitation et / ou les pièces jointes à l'appel d'offres sont protégés par le droit d'auteur. Veuillez consulter les conditions d’utilisation pour obtenir plus d'information.

    Détails

    Langue(s)
    Anglais, Français
    Région(s) de livraison
    Nouveau-Brunswick
    Région de l'appel d'offres
    Nouveau-Brunswick
    Méthode d'approvisionnement
    Concurrentielle – Invitation ouverte à soumissionner

    Soutien aux petites et moyennes entreprises

    Si vous avez des questions concernant cette occasion de marché, veuillez communiquer avec l'agent de négociation des contrats, dont les coordonnées se trouvent sous l'onglet Coordonnées.

    Consultez notre page de soutien si vous avez besoin d'aide ou si vous avez des questions sur le processus d'approvisionnement du gouvernement, y compris sur la façon de soumissionner ou de s'inscrire dans SAP Ariba. Vous pouvez également contacter Soutien en approvisionnement Canada, qui dispose de bureaux à travers le Canada.

    Date de modification: