2023 Flood Recovery - Infrastructure Projects
Numéro de sollicitation BC310-413
Date de publication
Date et heure de clôture 2024/06/25 17:00 HAE
Date de la dernière modification
Description
Addendum No.1 - June 14, 2024 **CLOSING DATE EXTENDED TO JUNE 25TH 2024 @ 2 PM
The Owner is seeking to engage a general contractor to complete the various infrastructure recovery projects related to the 2023 Cache Creek Flood. There are four (4) separate projects, which will need to be invoiced independently. All works will be done in accordance with MMCD and supplemental specifications outlined in the enclosed sample agreement. The completion of the following work is expected (approximate quantities):
Project A – Todd Road Bridge Repairs
Project B – Fire Department Apron
The Owner is seeking to engage a general contractor to complete the various infrastructure recovery projects related to the 2023 Cache Creek Flood. There are four (4) separate projects, which will need to be invoiced independently. All works will be done in accordance with MMCD and supplemental specifications outlined in the enclosed sample agreement. The completion of the following work is expected (approximate quantities):
Project A – Todd Road Bridge Repairs
- Remove and dispose of broken asphalt and base material.
- Supply and compact structural fill to return bridge approaches to original contours.
- Reestablish rip rap armoring along shoreline
- Construct lock block retaining wall to protect timber piles.
- Supply and install concrete Deadman blocks and tie to existing abutment wall.
- Supply asphalt, base and subbase material to repave Approximately 160m2 of road on bridge approaches.
- Replace bridge deck wear material – 170 pieces 4”x10”x16’ No.2 or better Douglas fir.
- 1 - Remove and replace Storm manhole
- 1 - Remove and replace Hydrant assembly
- 1 – Relocate gate valve
Project B – Fire Department Apron
- Remove and dispose of existing concrete apron and reinforcement
- Form and pour new reinforced concrete apron. Approx 200 m2
- Provide traffic control on Stage Road during construction.
- Saw cut, remove and dispose of existing asphalt road, curb, and sidewalk at excavation limits.
- Remove and reinstate street light conduit and chain link fence.
- Excavate and disassemble concrete block retaining wall. Reconstruct wall including geotextile and geogrid. Approx 20 m2 of wall face area.
- Replace approx. 20 m2 of Concrete sidewalk and 13 linear meter of curb and gutter as per MMCD standard drawing C-2.
- Replace approximately 30 m2 of Asphalt roadway.
- Provide traffic control on Hwy 97 during construction.
- Remove and replace approx. 125 m2 concrete sidewalk and 66 linear meter of curb and gutter as per MMCD standard drawing C-3.
Activity Date NRFP Release June 4, 2024 NRFP Closing Time, 2:00pm Pacific Standard Time June 25, 2024 Preferred Proponent selection and commencement of any negotiations leading to a completed agreement June 21, 2024 Preferred date of Project construction commencement July 2, 2024
Durée du contrat
Voir la description ci-dessus pour voir tous les détails.
Accords commerciaux
-
Veuillez consulter la description ou les documents de l'appel d'offres
Coordonnées
Organisation contractante
- Organisation
-
Village of Cache Creek
- Adresse courriel
- kkraan@true.bc.ca
Détails de l'offre
Les détails complets de cette occasion de marché sont disponibles sur un site tiers
Cliquez sur le bouton ci-dessous pour vous rendre vers ce site Web. Le site tiers pourrait exiger la création d’un compte personnel pour consulter l’occasion de marché ou pour soumissionner. Les informations reliées aux frais encourus pour accéder aux détails complets sont indiqués sous l’onglet Description.