This contract was awarded to:
REQUIREMENT
Parks Canada Agency requires a contractor to complete select pavement and concrete barrier replacement on the Trans-Canada Highway 1 between Km 15.96 and Km 19.90 in Glacier National Park, BC. Other work includes new sub-drain installations and additional paved drainage spillways to prevent slope erosion.
See specifications and drawings for further details on the requirement of this project.
PERIOD OF CONTRACT
The Contractor must perform and complete the Work by August 31, 2022